Westland Street & Westridge Drive Intersection Closure: April 27-May 11

PROJECT LOCATION
Westland St. & Westridge Dr. intersection

TYPE OF WORK
Final underground water, sanitary and storm sewer tie-ins for phase one of the Tillotson subdivision

SCHEDULE

  • Start Date: April 27, 2026
  • End Date: May 11, 2026
  • Hours: Monday to Saturday, 7 a.m. to 7 p.m.

IMPACTS

  • There will be “local access only” on Westland Street from Big Rock Trail to Westridge Road
  • Digital message boards in place 
  • Detours will be in place 24/7
  • No impact on local residents' direct driveway access 

WHAT TO EXPECT

  • Construction crews, heavy equipment and noise during working hours
  • Traffic detours in place; please follow detour signage
  • Expect delays at traffic lights in the area

WHY THIS WORK IS HAPPENING

To complete the final underground water, sanitary and storm sewer tie-ins for phase one of the Tillotson subdivision.

Image
Tillotson closure and detours map