Project Location
75 Wolf Cres (Wedderburn), west of Banister Drive and East of Northridge Drive
Type of Work
Underground deep utility (water, sanitary and storm sewer) tie-ins.
Schedule
- Start Date: May 25, 2026
- End Date: June 5, 2026
- Hours: Monday to Sunday, 7 a.m. to 7 p.m.
Impacts
- Full road closure along Wolf Crescent running north/south
- Detours in place 24/7
- There will be no impacts on residential access as a result of the construction work
What To Expect
- Construction crews, heavy equipment and noise during working hours
- Traffic signage directing detours.
Why This Work is Happening
To allow a new housing complex in Wedderburn to tie into the main water, sanitary and storm sewer lines.