Rivers Edge Infrastructure Improvements

Category
Development - Engineering & Planning
Status
In Progress
In 2025, the Town received more than $5 million from the Government of Alberta through the Local Growth and Sustainability Grant (LGSG), enabling critical infrastructure upgrades in the River's Edge area to move forward sooner. The project will modernize underground utilities, improve connections between downtown and the riverfront, and create a more accessible, welcoming, and vibrant community while supporting the vision outlined in Our Plan for Downtown (Downtown Area Redevelopment Plan).
 
Construction began in 2025 and continues through the 2026 construction season, with work being completed in phases.

Planned Improvements

What to Expect During Construction

Q&A

Phase 1
Deep utility construction
Completed
2025
Phase 1A
Sewer and road upgrades; sewer and road rehabilitation; and parking upgrades.
Started
Summer to Fall 2026
Phase 2
Deep Utility and road upgrades; flood protection, active transportation, streetlighting, and intersection improvements.
Future
Spring 2027