Typically, an applicant will be required to submit engineering design drawings that are prepared by a professional Engineer on the construction of the subdivision, including roadways, sidewalks, deep utility mains, and grading information.
Once the engineering design drawings are accepted, the applicant will enter into a subdivision servicing agreement. The agreement spells out the requirements for construction as well as securities and off-site levy payments required by the Town. The applicant has two years to construct the subdivision after entering into the subdivision servicing agreement.
If there are any public landscaped areas, such as boulevard trees or municipal reserve lands, the applicant will also be required to submit detailed Landscape Plans prepared by a Landscape Architect.
Upon satisfying any prior to registration conditions of approval, the applicant can submit the legal plans and documents for endorsement by Town. The legal plan, or ‘linen’, provides an accurate record of the survey markers placed in the ground, in the form of iron pins, from which dimensions are taken. It shows detail as to location, orientation, and size of all parcels.
The applicant has one year following approval of the subdivision to submit the endorsement package. If the applicant is unable to complete the prior to endorsement conditions within that one year period they can apply for an extension to the approval period.
Once endorsement has been issued by Town, the applicant has one year to register the Plan of Subdivision and associated requirements at the Land Title Office.
More information:
Infrastructure Design and Construction Specifications
Subdivision Endorsement Submission Requirements