Work on 32nd St b/w Crystal Green Wy & Crystal Green Ln until Aug 28

Project Location

Along the east side of 32nd Street, between Crystal Green Way and Crystal Green Lane.

Type of Work

Extension of the sanitary trunk main and installation of a new manhole at the intersection of 32nd Street and Crystal Green Lane. Work will take place along the east side of 32nd Street.

Schedule

  • Start Date: August 11, 2026
  • End Date: August 28, 2026
  • Hours: Monday to Saturday, 7 a.m. to 7 p.m.

Traffic & Pedestrian Impacts 

  • 32nd St East and the intersection at Crystal Green Lane will remain open to traffic during construction.
  • Digital message boards and signage will be in place to guide traffic and pedestrians.
  • Traffic delays are expected, especially during peak travel times.
  • The sidewalk on the east side of 32nd Street will be closed, with signed pedestrian detours available.
  • Traffic and pedestrian detours may remain in place 24 hours a day, as required, throughout construction.
  • Direct driveway access for nearby residents is expected to remain available.

What to Expect

  • Traffic will continue to move through the area; expect temporary traffic and pedestrian detours will occur during construction activities.
  • Construction crews, heavy equipment and increased noise during working hours.
  • Possible delays at nearby intersections and traffic signals.
  • Please slow down, follow all posted signs and traffic-control measures and use extra caution when travelling through the work zone.

Why This Work is Happening 

This work is required to extend the existing sanitary trunk main and install a new manhole as part of the off-site servicing work for the Ridgemont Phase 1 development.