Project Location
Intersection of Crystal Green Lane and 32nd Street
Type of Work
Completion of underground water and sanitary sewer utilities
Schedule
Start: August 5, 2026
End: August 31, 2026
Hours: Monday to Saturday, 7 a.m. to 7 p.m.
Impacts
- No road closures or traffic disruptions are expected, although construction activity will take place close to 32nd Street
- Speed reductions near the construction site
What to Expect
- Construction crews, heavy equipment and noise during working hours
- Access maintained for all properties that use Crystal Green Lane, with posted signage directing traffic via a gravel access road
Why is this Work Happening?
This work is required to connect the first phase of the Ridgemont subdivision to existing water, sanitary and storm sewer infrastructure.