News Releases


 

March 2014

Schedule

  • Schedule has been revised to Substantial Completion on June 30th, 2014 with Final Completion July 31st, 2014
  • Schedule has been affected with the two main issues being:
  • Manpower shortages related to the construction market and flood
  • Weather related conditions affecting site and work progress

Site Progress

  • Exterior wall cladding is 95%, less the South wall
  • 64th Street is 95% complete, less road gravel and ditch top soil
  • Plumbing, HVAC & electrical rough-in is 95% complete in the front of house
  • Plumbing, HVAC & electrical rough-in is 70% in Fieldhouse
  • Drywall on main floor is 95% taped
  • Second Floor final paint coat has started
  • Second Floor T-Bar Ceiling has begun and is 95% complete in Front of House
  • Fire suppression is 95% complete in Fieldhouse, 75% in Team Rooms
  • Deep services off site are 95% complete
  • Pump house construction exterior finishes 100%, interior of Pump house 80% complete, still awaiting units from Eaton
  • Running Track structure is 95% complete the remaining is outstanding for access
  • Bench millwork is 35% complete in Block A Team Rooms
  • Hollow core 100% complete
  • Hollow core topping 100% complete
  • Masonry for main floor of Fieldhouse is 100%, second floor masonry 50% complete
  • Field # 2 & #4 slab on grades have been poured
February 2014

Schedule
  • Schedule has been revised to Substantial Completion on June 30th, 2014 with Final Completion July 31st, 2014
  • Schedule has been affected with the two main issues being:
  • Manpower shortages related to the construction market and flood
  • Weather related conditions affecting site and work progress
Site Progress

  • Exterior wall cladding is 95%, less the South wall
  • 64th Street is 95% complete, less road gravel and ditch top soil
  • Plumbing, HVAC & electrical rough-in is 95% complete in the front of house
  • Plumbing, HVAC & electrical rough-in is 60% in Fieldhouse
  • Drywall on main floor is 90% taped
  • Second Floor has been prime painted and intermediate first coat complete
  • Second Floor T-Bar Ceiling has begun and is 25% complete in Front of House
  • Fire suppression is 95% complete in Fieldhouse, 60% in Team Rooms & 100% in Front of House
  • Deep services off site are 95% complete
  • Pump house construction exterior finishes 95%, interior of Pump house 75% complete
  • Running Track structure is 95% complete the remaining is outstanding for access
  • Bench millwork is 35% complete in Block A Team Rooms
  • Hollow core 80% complete
  • Masonry for main floor of Fieldhouse is 98% complete

Construction Management Report February 2014 (717 KB) Adobe

December

  • Schedule has been revised to Substantial Completion on June 30th, 2014 with Final Completion July 31st, 2014

Schedule has been affected with the two main issues being:

  • Manpower shortages related to the construction market and flood
  • Weather related conditions affecting site and work progress

Site Progress

  • Exterior wall cladding is 95%, less the South wall
  • 64th Street is 95% complete, less road gravel and ditch top soil
  • Plumbing, HVAC & electrical rough-in is 70% complete in the front of house
  • Plumbing, HVAC & electrical rough-in is 40% in Fieldhouse
  • Slab on grade Team Rooms Block B is complete
  • Main and second floor front of house steel stud framing is 100% complete
  • Drywall on second floor taped and sanded 95% and main floor boarded 100% taped 50%
  • EPDM roof is 98% complete only cap flashings remain
  • Underground mechanical for Team Rooms Block B is 100% complete
  • Fire suppression is 95% complete
  • Deep services off site are 95% complete
  • Pump house construction exterior framing complete & SOG has been poured
  • Clear story windows for the Fieldhouse 100% complete
  • Apolic panels are 100%
  • Running Track structure is 80% complete
  • Transformer installed and awaiting permanent power
Scott Builders December 2013 Monthly Construction Management Report (714 KB) Adobe
September 2013

Schedule
  • Schedule has been revised and are currently meeting all targets

Site Progress
  • Exterior wall cladding is 90% complete
  • Roof cladding is 95% complete
  • Main sanitary trunk line is 90% complete
  • 64th Street is 95% complete
  • Steel studs are complete on exterior walls for the front of house
  • Plumbing, HVAC & electrical rough-in is 65% complete in the front of house
  • Slab on grade for front of house has been poured
  • Main and second floor front of house steel stud framing is 75% complete and drywall has begun
  • Stucco has been completed
  • EPDM roof is 95% complete only cap flashings remain
  • Front of house glazing is 95% complete as are missing front door
  • Strip footing for team rooms is 50% complete
  • Fire suppression is 25% complete
  • Deep services off site are 30% complete

Sub-Trades

  • Waterston Contracting is installing the roof transition
  • Apex is excavating and backfilling storm line to pond and slab prep
  • Sani-Tech Mechanical continue rough-in
  • Atomic continues installation of interior wall steel and drywall on front of house
  • Amelco continues with rough-in in the front of house
  • Desa Glass continues installing windows on front of house
  • Volker Stevin continues site road work and the water & sanitary mains
  • CCS Contracting continues the EPDM roof
  • T.A.T Group completed the stucco on the front of house
  • Cousins Concrete is working on the footings for the team rooms
  • Stoughton Fire Protection has begun front of house coverage
Safety
  • We have had no incidents in the month of September
  • Our subtrades have one First-Aid in the month of September

Scott Builders September 2013 Monthly Construction Management Report (612 KB) Adobe
March 2013

Schedule

  • Schedule has been revised and are currently meeting all targets

Site Progress

  • Pre-Engineered Metal Building re-erection is 65% complete for primary steel
  • 64th Street is 60% complete until spring
  • Backfill of grade beams is 90% complete
  • Elevator shaft is 100% poured and block work complete
  • Engineered repairs on anchor bolts is 100% complete

Sub-Trades

  • Abacus Steel has completed repairing the anchor bolts
  • Waterston Contracting has begun re-erection of the metal building
  • Apex is backfilling and compacting and has excavated the elevator pit
  • Cousins Concrete have been forming, pouring and striping the elevator pit
  • LMS Reinforcing completed installing the reinforcing in the elevator pit
  • Majestic Masonry has begun work on the elevator shaft

Safety

  • We have had no incidents in the month of March
  • Our subtrades have had no incidents in the month of March
November 2012 Update

Schedule

  • We continue to monitor the schedule

Site Progress

  • Pre-Engineered Metal Building has been 100% delivered
  • Pre-Engineered Metal Building shake out is started
  • 64th Street is 60% complete
  • Site and Building grading and fill is 95% complete
  • Piles are 100% complete
  • Concrete grade beams and pile caps are 70% complete
  • Backfill of grade beams is 50% complete

Sub-Trades

  • We currently have 4 sub-trades working on site
  • APEX Earth Works is working on site work and building excavation
  • AGRA Foundations Ltd. have completing the piles
  • Cousins Concrete and Construction Inc. is forming, pouring and striping grade beams
  • Waterston Contracting Ltd. Has unloaded and sorted the Metal Building for erection
  • LMS Reinforcing Steel Group is on site installing the reinforcement for the grade beams

Safety

  • We have had no incidents in the month of November
  • Our subtrades have had no incidents in the month of November
Montly Construction Management Report
 

August 2012 Update

Schedule
• We have officially started the project. The access road began on August 15, 2012 Site Progress
• We have mobilized our site office
• Survey of the access road has been completed
• Striping and grading continues

Sub-Trades
• We currently have 2 sub trades onsite

Design/Permits
• Design work continues
• We are waiting for approval on the booster pump narrative from the MD
• We have submitted revised site servicing plans

Contracts/Change Notices
• We need to finalize the contract and final numbers
• Site work costs are being tendered

Safety
• No incidents

News Releases & Documents

Montly Construction Management Reports

News Releases

Documents
Ground Breaking MayorGround Breaking Ceremony

To celebrate the start of construction, a ground-breaking ceremony was held on the acquired parcel of land near the junction of Highway 7 and the Aldersyde overpass on Thursday, July 12.
 
The multi-purpose facility is a joint development of recreational facilities between the MD of Foothills and the Town of Okotoks that is anticipated to take approximately 15 months to compete.
 
Representatives from the MD of Foothills and the Town of Okotoks Councils attended to celebrate the beginning of this new and exciting project
 
Background

Foothills-Okotoks Regional Indoor Field House Design Build Contract Awarded to Scott Builders Inc. The MD of Foothills and Town of Okotoks Councils have entered into agreement with Scott Builders Inc. for a design/build contract for the Foothills-Okotoks Field House project. The multi-purpose facility will be located near the junction of Highway 7 and the Aldersyde overpass.

The Foothills-Okotoks Field House will include the following key components:

  1. 4 playing fields each 85 ft x 200 ft
  2. training area with locker rooms and team rooms
  3. administrative offices, meeting & multi‐purpose rooms
  4. a walking/running track
  5. construction and installation of roads and utilities to service the site

This flexible indoor facility will meet the needs of children, youths and adults in the community and will be sustainable in terms of business and market opportunities. Construction is anticipated to commence in mid July with substantial completion by September 2013.

In August 2010 the MD of Foothills and Town of Okotoks with the assistance of JR Huggett Co., selected a design- build construction approach to manage the Foothills-Okotoks Field House project. Twelve proposals were received, with 4 design teams short listed for the request for proposal phase and Scott Builders Inc. was selected.
Build Contract Awarded to Scott Builders Inc. (82 KB) Adobe